iasgroup was engaged to undertake fabric maintenance of the main deck, process decks and support structures on an FPSO in the north west of Australia. These areas required remediation where it had been established that the existing coating system had broken down.
The project had the following specifications:
Structure | FPSO - Decks & Supports |
Application Type | Blast and coating application |
Operating Environment | Offshore |
Remediation Area | 800m2 (initial scope) |
Surface Preparation | Sa2.5 & WJ-2 |
Method |
UHP Water Jetting Low Dust Dry Abrasive Blasting - SpongeJetTM Protective Coatings |